Orascom Construction PLC (ADX:ORAS)
د.إ 49.82 -0.020 (-0.04%) Market Cap: 5.49 Bil Enterprise Value: 1.88 Bil PE Ratio: 6.72 PB Ratio: 1.67 GF Score: 52/100

Half Year 2024 Orascom Construction PLC Earnings Call Transcript

Aug 28, 2024 / NTS GMT

Key Points

Positve
  • Orascom Construction PLC (CAI:ORAS) achieved a revenue of $1.477 billion in H1 2024, showing steady progress.
  • The company improved its EBITDA and bottom line, with adjusted EBITDA increasing 65.2% year-on-year in Q2 2024.
  • The first phase of the 500-megawatt wind farm is ahead of schedule and expected to be operational in Q4 2024.
  • The U.S. operations showed strong performance with a 27.8% year-on-year increase in revenue, driven by data center and aviation projects.
  • BESIX contributed positively to profitability, with a 20% higher contribution in Q2 2024 compared to Q2 2023.
Negative
  • Group revenue decreased by 6.3% year-on-year to $711 million in Q2 2024, impacted by the devaluation of the Egyptian pound.
  • MEA revenue decreased by 29% year-on-year due to the EGP devaluation and completion of existing projects.
  • The group's total equity decreased to $674 million as of June 2024, primarily due to currency translation differences and dividend payouts.
  • Cash outflow from operations was $54.2 million in Q2 2024, mainly related to high progress on certain projects.
  • The EBITDA margin for U.S. operations dropped by 2.9% in Q2 and H1 2024.
Operator

Good day, everyone, and welcome to the Orascom Construction first-half 2024 results conference call. (Operator Instructions)

I'd now like to hand the call over to Osama Bishai, CEO. Please go ahead.

Osama Bishai
Orascom Construction PLC

Good afternoon, good morning, everyone. Well, I hope everybody had a good summer. For the H1 results for 2024, we have been progressing in a steady manner on all our fronts on the construction side. We have achieved a revenue of $1.477 billion on both the MENA and the U.S. side.

We have improved our EBITDA and bottom line as a KPI to our business. On the construction side, we are going to complete the first phase of our 500-megawatt wind farm ahead of schedule, and it should be operational in Q4 this year, which is between 2 to 3 months ahead of schedule. And the second phase will be done by early summer next year, which is, again, 2 to 3 months ahead of schedule. On our other construction, which is with the EPC work has been progressing such sectors to ourselves and we are progressing well, and we believe that

Already have an account? Log in
Get the full story
Access to All Earning Calls and Stock Analysis
30-Year Financial on one screen
All-in-one Stock Screener with unlimited filters
Customizable Stock Dashboard
Real Time Insider Trading Transactions
8,000+ Institutional investors’ 13F holdings
Powerful Excel Add-in and Google sheets Add-on
All data downloadable
Quick customer support
And much more...
7-Day Free Trial · Cancel Anytime
Subscription fee may be tax deductible.
Excellent
4.6 out of 5 Trustpilot