GoGold Announces Updated Mineral Resource and PEA with NPV of US$458M at Los Ricos South

Author's Avatar
Sep 12, 2023

PR Newswire

Shares Outstanding: 326,382,261
Trading Symbols: TSX: GGD
OTCQX: GLGDF

Increase of 55% in Measured & Indicated AgEq Ounces and Increase of 55% in NPV from previous January 2021 MRE and PEA

HALIFAX, NS, Sept. 12, 2023 /PRNewswire/ - GoGold Resources Inc. (TSX: GGD) (OTCQX: GLGDF) ("GoGold", "the Company") is pleased to release the results of its updated Preliminary Economic Assessment ("PEA") and Mineral Resource Estimate ("MRE") at its Los Ricos South ("LRS") Project located in Jalisco State, Mexico. The updated PEA and MRE include the addition of the Eagle concession to the Project, acquired in October 2022, as well as additional drilling completed in the Main Zone of the Project since the release of the initial PEA in January 2021.

Highlights of the PEA, with a base case silver price of US$23.75/oz and gold price of US$1,850/oz are as follows (all figures in US dollars unless otherwise stated):

  • After-Tax net present value ("NPV") (using a discount rate of 5%) of US$458 Million with an After-Tax IRR of 37% (Base Case);
  • 11-year mine life producing a total of 88 Million payable silver equivalent ounces ("AgEq"), consisting of 47 Million silver ounces, 493 Thousand gold ounces, and 14 Million pounds of copper;
  • Initial capital costs of $148 Million, including $19 Million in contingency costs, over an expected 18 month build, additional expansion capital of $69 Million, and sustaining capital costs of $72 Million over the life of mine ("LOM");
  • Average LOM operating cash costs of $8.15/oz AgEq, and all in sustaining costs ("AISC") of $9.02/oz AgEq
  • Average annual production of 8 Million AgEq oz;
  • Approximately half of LOM metal production is long hole underground ("UG"), and approximately half is open pit ("OP") mining;

"We are very pleased with the work completed by our consultants and our technical team on the Mineral Resource and PEA for Los Ricos South. The projected cash flows are very substantial, especially when combined with our Los Ricos North PEA that was completed in March of this year. With an NPV of US$458M at LRS and US$413M at LRN, we now have a total NPV of US$871M in our Los Ricos district. We continue to advance the studies and we will complete a Pre-Feasibility Study ("PFS") for LRS this fall," said Brad Langille, President and CEO. "The PFS is ongoing and we are currently completing the advanced geotechnical work with our consultants. We will also continue to focus our efforts on the mine plan as we believe further optimization opportunities can be made. With our strong balance sheet we will continue to advance the project rapidly."

Highlights of the updated Mineral Resource:

  • Increase of 55% in Measured & Indicated Silver Equivalent ("AgEq") Ounces from initial January 2021 MRE, with 39% increase in Measured & Indicated AgEq grade;
  • Inclusion of 1.9 Million tonnes Measured & Indicated at excellent grade of 516 g/t AgEq in underground Eagle Deposit;
  • Measured & Indicated Mineral Resource at LRS of 98.6 Million ounces AgEq grading 276 g/t AgEq contained in 11.1 Million tonnes ("Mt");
  • Increased confidence in MRE, with conversion of approximately 9 Million ounces AgEq from initial January 2021 Inferred Mineral Resources to Measured & Indicated, resulting in 11 Million ounces AgEq in Inferred Mineral Resources at LRS grading 248 g/t AgEq contained in 1.4 Mt;
  • Total Los Ricos Measured & Indicated Mineral Resources of 186 Million ounces AgEq, including Los Ricos North
  • Total Los Ricos Inferred Mineral Resources of 84 Million ounces AgEq, including Los Ricos North
Updated PEA Summary

The updated PEA was prepared by independent consultants P&E Mining Consultants Inc ("P&E"), with metallurgical test work completed by SGS Canada Inc.'s Lakefield office ("SGS"), geotechnical study by Golder & Associates of Tucson, process plant design and costing by D.E.N.M. Engineering Ltd., and environmental and permitting led by CIMA Mexico.

Following are tables and figures showing key assumptions, results, and sensitivities.

Table 1 – LRS PEA Key Economic Assumptions and Results

Assumption / Result

Unit

Value

Assumption / Result

Unit

Value

Total OP Plant Feed Mined

kt

9,367

Net Revenue

US$M

2,049

Total UG Plant Feed Mined

kt

4,325

Initial Capital Costs

US$M

148

Total Plant Feed Mined

kt

13,692

Expansion Capital Costs

US$M

69

Operating Strip Ratio

Ratio

7.4

Sustaining Capital Costs

US$M

72

Silver Grade1

g/t

125

OP Mining Costs

$/t Plant Feed

12.13

Gold Grade1

g/t

1.18

UG Mining Costs

$/t Plant Feed

43.85

AgEq Grade1

g/t

217

LOM Mining Costs

$/t Plant Feed

22.15

Silver Recovery

%

86

Operating Cash Cost

US$/oz AgEq

8.15

Gold Recovery

%

95

All in Sustaining Cost

US$/oz AgEq

9.02

Silver Price

US$/oz

23.75

Mine Life

Yrs

11

Gold Price

US$/oz

1,850

Average process rate

t/day

3,349

Copper Price

US$/lb

4.00

After-Tax NPV (5% discount)

US$M

458

Payable Silver Metal

Moz

46.8

Pre-Tax NPV (5% discount)

US$M

708

Payable Gold Metal

koz

493

After-Tax IRR

%

36.6

Payable Copper

Mlb

13.5

Pre-Tax IRR

%

49.1

Payable AgEq

Moz

88.2

After-Tax Payback Period

Yrs

2.3

1.

Grades shown are LOM average process plant feed grades including both OP and UG sources. External dilution of approximately
10% for OP material and 28% for UG material was incorporated in the mining schedule.

GoGold_Resources_Inc__GoGold_Announces_Updated_Mineral_Resource.jpg

Figure 1 above highlights the excellent post-tax cash flows associated with the LRS project. The economics of the project have been evaluated based on the base case scenario US$23.75/oz silver price and gold price of US$1,850/oz. As illustrated in the following sensitivity tables, the project remains robust even at lower commodity prices or with higher costs.

Table 2 – LRS PEA Gold and Silver Price Sensitivities

Sensitivity

Base
Case

Silver Price (US$/oz)

17

19

21

23.75

26

30

33

Gold Price (US$/oz)

1,324

1,480

1,636

1,850

2,025

2,337

2,571

After-Tax NPV (5%) (US$M)

185

266

346

458

548

710

831

After-Tax IRR (%)

19.7

25.1

30.2

36.6

41.6

49.9

55.7

After-Tax Payback (years)

3.6

3.0

2.6

2.3

2.1

1.7

1.6

Table 3 – LRS PEA Operating Cost and Capital Cost Sensitivities

Sensitivity

-20 %

-10 %

Base
Case

10 %

20 %

Operating Costs – NPV (US$M)

526

492

458

423

389

Operating Costs – IRR (%)

40.6

38.6

36.6

34.6

32.5

Capital Costs – NPV (US$M)

495

476

458

439

420

Capital Costs – IRR (%)

45.2

40.5

36.6

33.3

30.4

Capital and Operating Costs

The LRS Project has been envisioned as a combined underground and open pit mining operation, with contract underground mining in years one to seven of the mine plan, supplemented by contract open pit mining in years three to eleven.

The process plant is comprised of conventional crushing and grinding followed by cyanide tank leaching. Back end filtration is required to maximize water recycling (dry stack tailings) as well as a SART (sulfidation, acidification re-neutralization and thickening) circuit to re-generate cyanide back to the process and to produce a saleable Cu2S copper sulfide product. Water supply to the process plant is provided by a nearby seasonally charged water dam and high voltage grid power is provided by the local utility. Expansion capital includes the cost to increase the process plant capacity from 1,750 tonnes per day to 4,000 tonnes per day in year three.

Table 4 – LOM Capital Cost Estimate

Type

Initial

(US$k)

Expansion

(US$k)1

Sustaining

(US$k)

Total

(US$k)

Process Plant direct costs

54,475

42,700

12,125

109,300

Underground development

60,706

48,473

109,179

Pre-stripping

19,074

500

19,574

Infrastructure

9,980

1,250

11,230

Project indirect costs

3,750

3,750

Total

128,911

61,774

62,348

253,033

Contingency (15%)

19,337

6,747

9,352

35,436

Total

148,247

68,521

71,700

288,469

1. Expansion capital is not included in AISC calculation

Table 5 – Operating Costs (Average LOM)

Operating Costs (Average LOM)

US$/tonne

Plant Feed

US$/tonne
Rock

Open Pit Mining1

12.13

1.65

Underground Mining2

43.85

Total LOM Mining3

22.15

Processing ($/t processed)

27.10

General and Admin ($/t processed)

2.63

Total ($/t processed)

51.88

1.

Open pit mining costs include a double-benched waste rock and mineralized material
average unit cost of $1.47/t.

2.

Bulk underground long hole mining. $43.85 is the cost of in-stope mining, additional
development costs of $11.21/t mined are included in sustaining capital in table 4, providing
a total UG mining cost of $55.06/t.

3.

Average LOM mining cost of both open pit and underground.

Mining

The contract underground mining will involve long hole stoping and cemented paste back filling of the mined-out stopes. Approximately 10% of the underground feed to the process plant will be sourced in close proximity to historical workings. The open pit mining will be contracted and carried out by drill and blast followed by conventional loading and truck haulage to the waste rock storage facilities and the process plant.

Metallurgy

A metallurgical test program was carried out by SGS Lakefield of Ontario, Canada. The program included grinding and leaching as well as comminution testing. The leach samples comprised of drill core sampling rejects representing the various zones of the Mineral Resource and whole HQ drill core for the comminution work. This preliminary test program estimated average gold and silver respective metallurgical recoveries of 95% and 85%.

Surface Rights Agreement

The Company has an agreement with the Ejido of Cinco Minas, which owns the surface rights over all of those concessions included in this PEA. The agreement allows GoGold to mine and explore the 1,280 hectares of land that is owned by the local Ejido for a period of twelve years with an option to renew for a further twelve years.

Mineral Resource Estimate

The basis for the PEA is the Mineral Resource Estimate completed by P&E for the Los Ricos South Project located in Jalisco State, Mexico, which has an effective date of September 8, 2023, with an NI 43-101 compliant Technical Report to be filed within 45 days of this news release. A summary of the Mineral Resource Estimate is provided in Table 6.

Table 6: Los Ricos South Mineral Resource Estimate – Pit Constrained and Out-of-Pit(1-7)

Mining Area

Category

Tonnes

Average Grade

Contained Metal

Au

Ag

Cu

AuEq

AgEq

Au

Ag

Cu

AuEq

AgEq

(M)

(g/t)

(g/t)

( %)

(g/t)

(g/t)

(koz)

(koz)

(Mlb)

(koz)

(koz)

Pit
Constrained5

Measured

3.9

1.08

142

0.03

2.94

231

135.9

17,858

2.3

369.1

28,898

Indicated

2.8

0.68

89

0.03

1.87

146

60.7

8,022

1.9

167.3

13,097

M&I

6.7

0.91

120

0.03

2.49

195

196.6

25,880

4.2

536.4

41,995

Inferred

0.5

0.58

99

0.04

1.91

150

9.6

1,632

0.4

31.4

2,460

Out-of-Pit6,7

Measured

0.7

3.60

298

0.35

7.94

621

80.7

6,679

5.4

178.1

13,940

Eagle

Indicated

1.2

3.13

164

0.37

5.79

453

117.5

6,176

9.5

217.5

17,028

M&I

1.9

3.30

214

0.36

6.59

516

198.2

12,855

15.0

395.6

30,969

Inferred

0.1

3.63

122

0.54

6.00

470

7.8

261

0.8

12.9

1,006

Out-of-Pit6,7

Measured

1.1

1.22

194

0.06

3.79

297

44.7

7,093

1.6

138.8

10,865

Main

Indicated

1.4

1.58

178

0.21

4.18

327

71.5

8,013

6.6

188.4

14,753

M&I

2.5

1.42

185

0.15

4.00

313

116.2

15,106

8.1

327.2

25,618

Inferred

0.8

1.42

133

0.41

3.73

292

36.8

3,431

7.2

96.6

7,566

Total

Measured

5.7

1.42

172

0.07

3.72

291

261.4

31,631

9.3

686.0

53,703

Indicated

5.4

1.45

129

0.15

3.33

260

249.7

22,210

18.0

573.2

44,878

M&I

11.1

1.43

151

0.11

3.53

276

511.0

53,841

27.3

1,259.2

98,582

Inferred

1.4

1.22

120

0.28

3.17

248

54.1

5,325

8.5

140.9

11,033

1.

Mineral Resources which are not Mineral Reserves do not have demonstrated economic viability. The estimate of
Mineral Resources may be materially affected by environmental, permitting, legal, title, taxation, socio-political,
marketing, or other relevant issues.

2.

The Inferred Mineral Resource in this estimate has a lower level of confidence than that applied to an Indicated Mineral
Resource and must not be converted to a Mineral Reserve. It is reasonably expected that the majority of the Inferred
Mineral Resource could be upgraded to an Indicated Mineral Resource with continued exploration.

3.

The Mineral Resources in this news release were estimated in accordance with the Canadian Institute of Mining,
Metallurgy and Petroleum (CIM), CIM Standards on Mineral Resources and Reserves, Definitions and Guidelines
prepared by the CIM Standing Committee on Reserve Definitions and adopted by the CIM Council.

4.

Historically mined areas were depleted from the Mineral Resource model.

5.

The pit constrained AgEq cut-off grade of 38 g/t Ag was derived from US$1,800/oz Au price, US$23.00/oz Ag price, 85%
Ag and 95% Au process recovery, US$25/tonne process and G&A cost. The constraining pit optimization parameters
were $2.10/t mineralized material and waste mining cost, and 45-degree pit slopes.

6.

The out-of-pit AgEq cut-off grade of 130 g/t Ag was derived from US$1,800/oz Au price, US$23.00/oz Ag price, 85% Ag
and 95% Au process recovery, US$33/tonne process and G&A cost, and a $50/tonne mining cost. The out-of-pit Mineral
Resource grade blocks were quantified above the 130 g/t AgEq cut-off, below the constraining pit shell and within the
constraining mineralized wireframes. Out–of-Pit Mineral Resources are restricted to the Los Ricos and Rascadero Veins,
which exhibit historical continuity and reasonable potential for extraction by cut and fill and longhole mining methods.

7.

AgEq and AuEq were calculated at an Ag/Au ratio of 86.5:1 for pit constrained and 89.6:1 for out-of-pit.

GoGold_Resources_Inc__GoGold_Announces_Updated_Mineral_Resource.jpg

Mineral Resource Estimate Methodology – LRS

A total of 585 drill holes totalling 93,591 metres were used in the MRE.

P&E collaborated with GoGold personnel to develop the mineralization models, estimates, and reporting criteria for the Resources at Los Ricos. Mineralization models were initially developed by GoGold and were reviewed and modified by P&E. A total of eight individual mineralized domains have been identified through drilling, surface and historical underground sampling. The modeled mineralization domains are constrained by individual wireframes based on a 0.30 g/t AuEq cut-off for low-grade domains or 3.0 g/t AuEq for high-grade domains.

Mineralization wireframes were used as hard boundaries for the purposes of estimation.

A three-dimensional sub-blocked model, with 3m x